Canadian River-Muskogee and Muskogee-Seminole 345kV (GEN-2017-040)

Canadian River-Muskogee and Muskogee-Seminole 345kV is a 200.1 MW solar interconnection project in Ochiltree County, Texas with a current status of active. It is proposed to connect at Canadian River-Muskogee and Muskogee-Seminole 345kV.

200.1 MWCapacity
ActiveStatus
TXMarket
SolarTechnology

Project facts

Canonical nameCanadian River-Muskogee and Muskogee-Seminole 345kV
Queue IDGEN-2017-040
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketTX
TechnologySolar
Capacity200.1 MW
StateTexas
CountyOchiltree County
Point of interconnectionCanadian River-Muskogee and Muskogee-Seminole 345kV
Requested (queue) date2017-05-31
Proposed in-service date2026-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerOGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata