Carson-Wake 500kV (X2-076)

Carson-Wake 500kV is a 1,525.5 MW gas interconnection project in Brunswick, Virginia with a current status of operational.

1,525.5 MWCapacity
OperationalStatus
Market
GasTechnology

Project facts

Canonical nameCarson-Wake 500kV
Queue IDX2-076
Statusoperational
Source statusIn Service
Market
TechnologyGas
Capacity1,525.5 MW
StateVirginia
CountyBrunswick
Point of interconnection
Requested (queue) date2011-07-28
Proposed in-service date
Operational date2016-05-01
Withdrawn date
Developer
Utility / transmission ownerDominion

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata