Carvers Creek LLC is a 40.0 MW battery interconnection project in Gloucester, Virginia with a current status of withdrawn. It is proposed to connect at Owl Trap Switching Station 115kV.

40.0 MWCapacity
WithdrawnStatus
PJMMarket
BatteryTechnology

Project facts

Canonical nameCarvers Creek LLC
Queue IDAH1-355
Statuswithdrawn
Source statuswithdrawn
MarketPJM
TechnologyBattery
Capacity40.0 MW
StateVirginia
CountyGloucester
Point of interconnectionOwl Trap Switching Station 115kV
Requested (queue) date2021-09-10
Proposed in-service date2024-09-10
Operational date
Withdrawn date2025-03-25
DeveloperCarvers Creek, LLC
Utility / transmission ownerDominion

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.