Ceres BESS is a 202.7 MW other interconnection project in Hunt, Texas with a current status of operational. It is proposed to connect at Tap 138 kV 6883 QUINLAN NORTH SS - 6860 UNION VALLEY SS.

202.7 MWCapacity
OperationalStatus
HuntMarket
OtherTechnology

Project facts

Canonical nameCeres BESS
Queue ID26INR0464
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketHunt
TechnologyOther
Capacity202.7 MW
StateTexas
CountyHunt
Point of interconnectionTap 138 kV 6883 QUINLAN NORTH SS - 6860 UNION VALLEY SS
Requested (queue) date2024-10-29
Proposed in-service date
Operational date2028-08-10
Withdrawn date
DeveloperCeres BESS, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.