Hunt County, Texas — Interconnection Projects
The interXdata warehouse tracks 26 interconnection projects in Hunt, Texas, representing 2,524 MW of requested capacity.
26Total projects
1Active
20Operational
4Withdrawn
2,524 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Other | 9 | 1,324 MW |
| Battery | 3 | 542 MW |
| Solar | 9 | 510 MW |
| Gas | 5 | 148 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| 18-BRAVO BESS | 28INR0327 | Other | 407.0 MW | operational | Hunt, Texas |
| Egret Hill Storage | 21INR0519 | Other | 205.6 MW | withdrawn | Hunt, Texas |
| Fermata BESS | 27INR0461 | Other | 204.0 MW | operational | Hunt, Texas |
| Ceres BESS | 26INR0464 | Other | 202.7 MW | operational | Hunt, Texas |
| Turquoise Storage | 22INR0509 | Other | 196.2 MW | operational | Hunt, Texas |
| Cunningham Storage | 65410_SPUT | Battery | 190.0 MW | operational | Hunt, Texas |
| McMurtre Storage | 25INR0371 | Battery | 176.1 MW | suspended | Hunt, Texas |
| Mcmurtre Storage | 68171_MCMBA | Battery | 176.1 MW | active | Hunt, Texas |
| Pink Solar SLF | 22INR0281 | Solar | 152.4 MW | operational | Hunt, Texas |
| Power Lane II Gas | 27INR0489 | Gas | 104.4 MW | operational | Hunt, Texas |
| VALDIVIAN SOLAR | 25INR0246 | Solar | 74.9 MW | operational | Hunt, Texas |
| HATHOR SOLAR | 22INR0396 | Solar | 67.6 MW | withdrawn | Hunt, Texas |
| Signal Solar | 20INR0208 | Solar | 51.8 MW | operational | Hunt, Texas |
| MAKALU SOLAR | 22INR0425 | Solar | 50.2 MW | operational | Hunt, Texas |
| BT Signal Ranch | 67849_BTS | Solar | 50.0 MW | operational | Hunt, Texas |
| Powerlane Plant | 4195_ST3 | Other | 43.2 MW | operational | Hunt, Texas |
| Hallmark Solar | 18INR0056 | Solar | 43.0 MW | withdrawn | Hunt, Texas |
| Rubi Storage | 22INR0510 | Other | 40.0 MW | withdrawn | Hunt, Texas |
| Powerlane Plant | 4195_ST2 | Other | 25.0 MW | operational | Hunt, Texas |
| Powerlane Plant | 4195_ST1 | Gas | 18.8 MW | operational | Hunt, Texas |
| Sterling Solar (TX) | 61871_GEN1 | Solar | 10.0 MW | operational | Hunt, Texas |
| Leon Solar | 61532_GEN1 | Solar | 10.0 MW | operational | Hunt, Texas |
| Powerlane Plant | 4195_EP3 | Gas | 8.4 MW | operational | Hunt, Texas |
| Powerlane Plant | 4195_EP | Gas | 8.4 MW | operational | Hunt, Texas |
| Powerlane Plant | 4195_EP2 | Gas | 8.4 MW | operational | Hunt, Texas |
| Pink Storage SLF | 29INR0293 | Other | 0.0 MW | operational | Hunt, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| ABEI ENERGY&INFRASTRUCTURE LLC | 3 | 193 MW |
| Pink Solar, LLC | 2 | 152 MW |
| Ceres BESS, LLC | 1 | 203 MW |
| Fermata BESS, LLC | 1 | 204 MW |
| Hallmark Solar, LLC | 1 | 43 MW |
| Belltown Power | 1 | 40 MW |
| BT Cunningham Storage, LLC | 1 | 196 MW |
| Scout Energy Management, LLC | 1 | 407 MW |
| Coyote Crossing LLC | 1 | 206 MW |
| GEUS | 1 | 104 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Hunt County.
Start tracking with interXdata