Cherry Sage Solar 1 SLF (28INR0358)

Cherry Sage Solar 1 SLF is a 142.5 MW solar interconnection project in Concho, Texas with a current status of operational. It is proposed to connect at (#60423) TREADWELL 138kV..

142.5 MWCapacity
OperationalStatus
ConchoMarket
SolarTechnology

Project facts

Canonical nameCherry Sage Solar 1 SLF
Queue ID28INR0358
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketConcho
TechnologySolar
Capacity142.5 MW
StateTexas
CountyConcho
Point of interconnection(#60423) TREADWELL 138kV.
Requested (queue) date2025-04-25
Proposed in-service date—
Operational date2029-02-23
Withdrawn date—
DeveloperCherry Sage Solar 1 LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-12

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata