Chesterfield 230 kV (AG2-384 - moved to TC2)

Chesterfield 230 kV is a 60.0 MW battery interconnection project in Chesterfield, Virginia with a current status of active.

60.0 MWCapacity
ActiveStatus
—Market
BatteryTechnology

Project facts

Canonical nameChesterfield 230 kV
Queue IDAG2-384 - moved to TC2
Statusactive
Source statusActive
Market—
TechnologyBattery
Capacity60.0 MW
StateVirginia
CountyChesterfield
Point of interconnection—
Requested (queue) date2021-03-29
Proposed in-service date2031-12-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerDominion

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-01capacity_mw60.8260high
2026-10-01proposed_online_date—2031-12-31medium
2026-07-29new_project—activehigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata