Ciervo Wind (28INR0242)

Ciervo Wind is a 301.5 MW other interconnection project in Jim Hogg, Texas with a current status of operational. It is proposed to connect at Tap 345 kV 80355 DelSol7A - 80079 Cruce CKT 2.

301.5 MWCapacity
OperationalStatus
Jim HoggMarket
OtherTechnology

Project facts

Canonical nameCiervo Wind
Queue ID28INR0242
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketJim Hogg
TechnologyOther
Capacity301.5 MW
StateTexas
CountyJim Hogg
Point of interconnectionTap 345 kV 80355 DelSol7A - 80079 Cruce CKT 2
Requested (queue) date2024-12-19
Proposed in-service date
Operational date2028-12-31
Withdrawn date
DeveloperRWE Solar Development, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.