City Breeze Energy Storage (70455_BES)

City Breeze Energy Storage is a 140.0 MW battery interconnection project in Matagorda, Texas with a current status of active.

140.0 MWCapacity
ActiveStatus
ERCOMarket
BatteryTechnology

Project facts

Canonical nameCity Breeze Energy Storage
Queue ID70455_BES
Statusactive
Source status(V) Under construction, more than 50 percent complete
MarketERCO
TechnologyBattery
Capacity140.0 MW
StateTexas
CountyMatagorda
Point of interconnection—
Requested (queue) date—
Proposed in-service date2027-06-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerCity Breeze Energy Storage, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-11-01new_project—activehigh

Explore related data

Source last checked2026-11-01
Data last materially changed2026-11-01
Page data generated2026-11-26

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata