Clairemont Solar 1 (27INR0435)
Clairemont Solar 1 is a 251.8 MW solar interconnection project in Kent, Texas with a current status of operational. It is proposed to connect at 59908 Novaprime 345kV.
251.8 MWCapacity
OperationalStatus
KentMarket
SolarTechnology
Project facts
| Canonical name | Clairemont Solar 1 |
|---|---|
| Queue ID | 27INR0435 |
| Status | operational |
| Source status | SS Completed, FIS Started, IA |
| Market | Kent |
| Technology | Solar |
| Capacity | 251.8 MW |
| State | Texas |
| County | Kent |
| Point of interconnection | 59908 Novaprime 345kV |
| Requested (queue) date | 2025-01-28 |
| Proposed in-service date | — |
| Operational date | 2029-02-13 |
| Withdrawn date | — |
| Developer | Clairemont Solar LLC |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.