CO Queue Project 2021-G3 — Solar in Morgan County, Colorado

CO Queue Project 2021-G3 — Solar in Morgan County, Colorado is a 80.0 MW solar interconnection project in Morgan County, Colorado with a current status of withdrawn. It is proposed to connect at Hoyt 115-kV.

80.0 MWCapacity
WithdrawnStatus
COMarket
SolarTechnology

Project facts

Canonical nameCO Queue Project 2021-G3 — Solar in Morgan County, Colorado
Queue ID2021-G3
Statuswithdrawn
Source statusWithdrawn
MarketCO
TechnologySolar
Capacity80.0 MW
StateColorado
CountyMorgan County
Point of interconnectionHoyt 115-kV
Requested (queue) date2021-06-16
Proposed in-service date2024-12-15
Operational date
Withdrawn date
Developer
Utility / transmission ownerWestern Area Power Administration - Rocky Mountain Region

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: wapa-rm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata