Morgan County, County, Colorado — Interconnection Projects
Home / States / Colorado / Morgan County,
The interXdata warehouse tracks 22 interconnection projects in Morgan County,, Colorado, representing 5,914 MW of requested capacity.
22 Total projects
11 Active
2 Operational
9 Withdrawn
5,914 MW Requested capacity
Technology mix
Technology Projects Requested capacity Solar+Battery 7 2,264 MW Solar 8 1,488 MW Wind 4 1,412 MW Battery 3 750 MW
Projects
Project Queue ID Technology Capacity Status Location CO Queue Project GI-2021-30 — Solar in Morgan County, Colorado GI-2021-30 Solar 500.0 MW withdrawn Morgan County, Colorado CO Queue Project GI-2026-08 — Solar+Battery in Morgan County, Colorado GI-2026-08 Solar+Battery 500.0 MW active Morgan County, Colorado CO Queue Project GI-2024-06 — Solar+Battery in Morgan County, Colorado GI-2024-06 Solar+Battery 500.0 MW active Morgan County, Colorado CO Queue Project GI-2023-15 — Wind in Morgan County, Colorado GI-2023-15 Wind 400.5 MW withdrawn Morgan County, Colorado CO Queue Project GI-2023-14 — Wind in Morgan County, Colorado GI-2023-14 Wind 400.0 MW active Morgan County, Colorado CO Queue Project GI-2021-25 — Wind in Morgan County, Colorado GI-2021-25 Wind 362.0 MW withdrawn Morgan County, Colorado CO Queue Project GI-2025-07 — Solar+Battery in Morgan County, Colorado GI-2025-07 Solar+Battery 360.0 MW active Morgan County, Colorado CO Queue Project GI-2025-01 — Solar+Battery in Morgan County, Colorado GI-2025-01 Solar+Battery 300.0 MW active Morgan County, Colorado CO Queue Project GI-2020-15 — Wind in Morgan County, Colorado GI-2020-15 Wind 250.0 MW withdrawn Morgan County, Colorado CO Queue Project 5RSC-2024-11 — Battery in Morgan County, Colorado 5RSC-2024-11 Battery 250.0 MW active Morgan County, Colorado CO Queue Project 5RSC-2024-27 — Solar+Battery in Morgan County, Colorado 5RSC-2024-27 Solar+Battery 250.0 MW active Morgan County, Colorado CO Queue Project GI-2026-23 — Battery in Morgan County, Colorado GI-2026-23 Battery 250.0 MW active Morgan County, Colorado CO Queue Project GI-2021-31 — Battery in Morgan County, Colorado GI-2021-31 Battery 250.0 MW withdrawn Morgan County, Colorado Story 230 Substation GI-CS-2025-19 Solar 199.9 MW operational Morgan County,, Colorado Story 230 Substation GI-TC-2024-30 Solar 199.9 MW active Morgan County, Colorado Story 230 Substation GI-CS-2025-20 Solar 199.9 MW operational Morgan County,, Colorado CO Queue Project GI-2021-26 — Solar+Battery in Morgan County, Colorado GI-2021-26 Solar+Battery 183.7 MW withdrawn Morgan County, Colorado CO Queue Project 2024-G4 — Solar+Battery in Morgan County, Colorado 2024-G4 Solar+Battery 170.0 MW withdrawn Morgan County, Colorado CO Queue Project GI-2024-18 — Solar in Morgan County, Colorado GI-2024-18 Solar 150.0 MW active Morgan County, Colorado CO Queue Project 2024-G1 — Solar in Morgan County, Colorado 2024-G1 Solar 150.0 MW withdrawn Morgan County, Colorado CO Queue Project 2021-G3 — Solar in Morgan County, Colorado 2021-G3 Solar 80.0 MW withdrawn Morgan County, Colorado CO Queue Project 2026-G1 — Solar in Morgan County, Colorado 2026-G1 Solar 8.5 MW active Morgan County, Colorado
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked 2026-07-31
Data last materially changed 2026-08-27
Page data generated 2026-08-27
Provenance: psco-oasis; Southwest Power Pool — generator interconnection queue ; wapa-rm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.