CO Queue Project GI-2026-02 — Solar+Battery in Cheyenne County, Colorado

CO Queue Project GI-2026-02 — Solar+Battery in Cheyenne County, Colorado is a 250.0 MW solar+battery interconnection project in Cheyenne County, Colorado with a current status of active. It is proposed to connect at Goose Creek 345 kV Substation.

250.0 MWCapacity
ActiveStatus
COMarket
Solar+BatteryTechnology

Project facts

Canonical nameCO Queue Project GI-2026-02 — Solar+Battery in Cheyenne County, Colorado
Queue IDGI-2026-02
Statusactive
Source statusStudy to be started after completion of 7RSC Cluster
MarketCO
TechnologySolar+Battery
Capacity250.0 MW
StateColorado
CountyCheyenne County
Point of interconnectionGoose Creek 345 kV Substation
Requested (queue) date2026-04-24
Proposed in-service date2029-03-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerPublic Service Company Of Colorado

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: psco-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata