Cheyenne County County, Colorado — Interconnection Projects
The interXdata warehouse tracks 7 interconnection projects in Cheyenne County, Colorado, representing 2,549 MW of requested capacity.
7Total projects
6Active
0Operational
1Withdrawn
2,549 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 2 | 1,150 MW |
| Solar | 2 | 599 MW |
| Solar+Battery | 2 | 550 MW |
| Battery | 1 | 250 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| CO Queue Project GI-2020-14 — Wind in Cheyenne County, Colorado | GI-2020-14 | Wind | 700.0 MW | withdrawn | Cheyenne County, Colorado |
| CO Queue Project 5RSC-2024-16 — Wind in Cheyenne County, Colorado | 5RSC-2024-16 | Wind | 450.0 MW | active | Cheyenne County, Colorado |
| CO Queue Project GI-2025-09 — Solar in Cheyenne County, Colorado | GI-2025-09 | Solar | 400.0 MW | active | Cheyenne County, Colorado |
| CO Queue Project GI-2025-02 — Solar+Battery in Cheyenne County, Colorado | GI-2025-02 | Solar+Battery | 300.0 MW | active | Cheyenne County, Colorado |
| CO Queue Project GI-2026-02 — Solar+Battery in Cheyenne County, Colorado | GI-2026-02 | Solar+Battery | 250.0 MW | active | Cheyenne County, Colorado |
| CO Queue Project 5RSC-2024-10 — Battery in Cheyenne County, Colorado | 5RSC-2024-10 | Battery | 250.0 MW | active | Cheyenne County, Colorado |
| Burlington - Lamar 230 Line | GI-TC-2024-07 | Solar | 199.0 MW | active | Cheyenne County, Colorado |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: psco-oasis; Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Cheyenne County County.
Start tracking with interXdata