Colorado Bend I Expansion (21INR0512)

Colorado Bend I Expansion is a 78.0 MW gas interconnection project in Wharton, Texas with a current status of operational. It is proposed to connect at 42985 Dyann 138kV.

78.0 MWCapacity
OperationalStatus
ERCOTMarket
GasTechnology

Project facts

Canonical nameColorado Bend I Expansion
Queue ID21INR0512
Statusoperational
Source statusoperational
MarketERCOT
TechnologyGas
Capacity78.0 MW
StateTexas
CountyWharton
Point of interconnection42985 Dyann 138kV
Requested (queue) date2020-09-10
Proposed in-service date2023-05-26
Operational date2023-05-31
Withdrawn date
DeveloperColorado Bend I Power, LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata