Commodus 2 Wind (29INR0033)

Commodus 2 Wind is a 641.5 MW other interconnection project in Swisher, Texas with a current status of operational. It is proposed to connect at Tapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900).

641.5 MWCapacity
OperationalStatus
SwisherMarket
OtherTechnology

Project facts

Canonical nameCommodus 2 Wind
Queue ID29INR0033
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketSwisher
TechnologyOther
Capacity641.5 MW
StateTexas
CountySwisher
Point of interconnectionTapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900)
Requested (queue) date2025-03-03
Proposed in-service date
Operational date2029-07-30
Withdrawn date
DeveloperIP Blackwell II, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.