CONDUIT ENERGY STORAGE (2105)

CONDUIT ENERGY STORAGE is a 500.0 MW battery interconnection project in San Bernardino, California with a current status of active. It is proposed to connect at Lugo Substation 500 kV.

500.0 MWCapacity
ActiveStatus
NOLMarket
BatteryTechnology

Project facts

Canonical nameCONDUIT ENERGY STORAGE
Queue ID2105
Statusactive
Source statusACTIVE
MarketNOL
TechnologyBattery
Capacity500.0 MW
StateCalifornia
CountySan Bernardino
Point of interconnectionLugo Substation 500 kV
Requested (queue) date2021-04-15
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerSCE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectactivehigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata