Coyote Wind (17INR0027b)

Coyote Wind is a 242.6 MW other interconnection project in Scurry, Texas with a current status of operational. It is proposed to connect at 11305 Dermott 345kV.

242.6 MWCapacity
OperationalStatus
ScurryMarket
OtherTechnology

Project facts

Canonical nameCoyote Wind
Queue ID17INR0027b
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketScurry
TechnologyOther
Capacity242.6 MW
StateTexas
CountyScurry
Point of interconnection11305 Dermott 345kV
Requested (queue) date2015-04-22
Proposed in-service date
Operational date2025-12-01
Withdrawn date
DeveloperCoyote Wind
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata