CPS Energy AvR1CT2 Rotor Replacement (25INR0531)
CPS Energy AvR1CT2 Rotor Replacement is a 23.2 MW gas interconnection project in Bexar, Texas with a current status of operational. It is proposed to connect at 5475 Braunig 345kV.
23.2 MWCapacity
OperationalStatus
BexarMarket
GasTechnology
Project facts
| Canonical name | CPS Energy AvR1CT2 Rotor Replacement |
|---|---|
| Queue ID | 25INR0531 |
| Status | operational |
| Source status | SS Completed, FIS Completed, No IA |
| Market | Bexar |
| Technology | Gas |
| Capacity | 23.2 MW |
| State | Texas |
| County | Bexar |
| Point of interconnection | 5475 Braunig 345kV |
| Requested (queue) date | 2023-10-13 |
| Proposed in-service date | — |
| Operational date | 2026-08-05 |
| Withdrawn date | — |
| Developer | CPS Energy |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata