Crowded Star Solar II (22INR0274)

Crowded Star Solar II is a 189.5 MW solar interconnection project in Jones, Texas with a current status of operational. It is proposed to connect at tap 345kV 68001 Claytonville – 68004 Phantom Hill c2 (New Substation: Open Sky 68014).

189.5 MWCapacity
OperationalStatus
JonesMarket
SolarTechnology

Project facts

Canonical nameCrowded Star Solar II
Queue ID22INR0274
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketJones
TechnologySolar
Capacity189.5 MW
StateTexas
CountyJones
Point of interconnectiontap 345kV 68001 Claytonville – 68004 Phantom Hill c2 (New Substation: Open Sky 68014)
Requested (queue) date2020-03-26
Proposed in-service date
Operational date2026-09-01
Withdrawn date
DeveloperJones City Solar II, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.