Cunningham 500 kV (AH1-723 - moved to TC2)

Cunningham 500 kV is a 776.0 MW gas interconnection project in Fluvanna, Virginia with a current status of active.

776.0 MWCapacity
ActiveStatus
—Market
GasTechnology

Project facts

Canonical nameCunningham 500 kV
Queue IDAH1-723 - moved to TC2
Statusactive
Source statusActive
Market—
TechnologyGas
Capacity776.0 MW
StateVirginia
CountyFluvanna
Point of interconnection—
Requested (queue) date2025-04-06
Proposed in-service date2031-05-30
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerDominion

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-01proposed_online_date—2031-05-30medium
2026-07-29new_project—activehigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.