Darkwood Solar (27INR0049)

Darkwood Solar is a 150.8 MW solar interconnection project in Comanche, Texas with a current status of operational. It is proposed to connect at Tap 345KV 1900 Comanche Peak to 1440 Comanche SS .

150.8 MWCapacity
OperationalStatus
ComancheMarket
SolarTechnology

Project facts

Canonical nameDarkwood Solar
Queue ID27INR0049
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketComanche
TechnologySolar
Capacity150.8 MW
StateTexas
CountyComanche
Point of interconnectionTap 345KV 1900 Comanche Peak to 1440 Comanche SS
Requested (queue) date2023-06-28
Proposed in-service date
Operational date2027-09-20
Withdrawn date
DeveloperMustang Creek Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.