Deepwater (21INR0007)

Deepwater is a 462.2 MW gas interconnection project in Harris, Texas with a current status of withdrawn. It is proposed to connect at 40450 Deepwater 345kV.

462.2 MWCapacity
WithdrawnStatus
ERCOTMarket
GasTechnology

Project facts

Canonical nameDeepwater
Queue ID21INR0007
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologyGas
Capacity462.2 MW
StateTexas
CountyHarris
Point of interconnection40450 Deepwater 345kV
Requested (queue) date2017-12-04
Proposed in-service date2021-04-30
Operational date
Withdrawn date2020-04-06
DeveloperAES DE DEVCO NC LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata