Duffy BESS (26INR0250)

Duffy BESS is a 241.1 MW other interconnection project in Matagorda, Texas with a current status of operational. It is proposed to connect at Tap 345kV WAP to STP CKT39 (PTI# 5915-44000 CKT 39).

241.1 MWCapacity
OperationalStatus
MatagordaMarket
OtherTechnology

Project facts

Canonical nameDuffy BESS
Queue ID26INR0250
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketMatagorda
TechnologyOther
Capacity241.1 MW
StateTexas
CountyMatagorda
Point of interconnectionTap 345kV WAP to STP CKT39 (PTI# 5915-44000 CKT 39)
Requested (queue) date2023-08-21
Proposed in-service date
Operational date2026-12-31
Withdrawn date
DeveloperDuffy Energy Storage LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata