EAST WINAMAC - MONTICELLO 138.0kV (J3257)

EAST WINAMAC - MONTICELLO 138.0kV is a 190.0 MW solar interconnection project in Pulaski, Indiana with a current status of withdrawn. It is proposed to connect at EAST WINAMAC - MONTICELLO 138.0kV.

190.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameEAST WINAMAC - MONTICELLO 138.0kV
Queue IDJ3257
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity190.0 MW
StateIndiana
CountyPulaski
Point of interconnectionEAST WINAMAC - MONTICELLO 138.0kV
Requested (queue) date2024-04-18
Proposed in-service date2026-10-01
Operational date2026-10-01
Withdrawn date2025-09-30
Developer
Utility / transmission ownerNORTHERN INDIANA PUBLIC SERVICE COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.