NORTHERN INDIANA PUBLIC SERVICE COMPANY — Interconnection Queue Projects
NORTHERN INDIANA PUBLIC SERVICE COMPANY is associated with 127 tracked interconnection projects representing 23,890 MW of requested capacity.
Entity resolution: this utility / transmission entity rolls up 4 source organization name(s) that were auto-matched into a single canonical cluster. Attribution is inferred from source records and may include related special-purpose entities.
127Projects
1Active
62Operational
64Withdrawn
23,890 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 64 | 10,818 MW |
| Other | 18 | 4,557 MW |
| Battery | 28 | 4,403 MW |
| Wind | 14 | 2,724 MW |
| Gas | 3 | 1,388 MW |
Geographic footprint
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| MISO Queue Project J4324 — Generation in Starke, the U.S. | J4324 | — | 976.1 MW | operational | Starke, — |
| MISO Queue Project J4342 — Generation in an unlisted county, the U.S. | J4342 | — | 976.1 MW | operational | — |
| SCHAHFER GEN STA | R5062 | Gas | 732.7 MW | withdrawn | Jasper, Indiana |
| Reynolds--Burr Oak 345kV line | J2846 | Solar | 700.0 MW | operational | Pulaski, Indiana |
| Leesburg 345 kV | J2443 | Battery | 500.0 MW | withdrawn | Kosciusko, Indiana |
| Stillwell to Babcock 345kV Transmission Line | J3215 | Gas | 500.0 MW | withdrawn | LaPorte, Indiana |
| Other_ | J3931 | Solar | 500.0 MW | operational | Jasper, Indiana |
| MISO Queue Project J4404 — Generation in an unlisted county, the U.S. | J4404 | — | 490.0 MW | operational | — |
| Reynolds 345 kV Substation | J2496 | Battery | 400.0 MW | operational | White, Indiana |
| Taping 'Reynolds / 17REYNOLDS (255205)' to 'Burr Oak / 17BURR_OAK (255101)' 22.4mi from Reynolds 345 | J3119 | Solar | 350.0 MW | withdrawn | Pulaski, Indiana |
| MISO Queue Project J4463 — Generation in an unlisted county, the U.S. | J4463 | — | 300.0 MW | operational | — |
| MISO Queue Project J4272 — Generation in an unlisted county, the U.S. | J4272 | — | 300.0 MW | operational | — |
| SCHAHFER GEN STA - ST. JOHN 345.0kV | J2215 | Battery | 300.0 MW | operational | Lake, Indiana |
| MISO Queue Project J4313 — Generation in an unlisted county, the U.S. | J4313 | — | 300.0 MW | operational | — |
| Other_ | J3910 | Wind | 300.0 MW | operational | Newton, Indiana |
| Schahfer-St. John 345kV Line Tap | J1058 | Solar | 300.0 MW | operational | Lake County, Indiana |
| LEESBURG - DEEDSVILLE (DUKE) 345.0kV | J3499 | Solar | 300.0 MW | withdrawn | Kosciusko, Indiana |
| MISO Queue Project J4467 — Generation in an unlisted county, the U.S. | J4467 | — | 300.0 MW | operational | — |
| BURR OAK - LEESBURG 345.0kV | J3693 | Battery | 300.0 MW | withdrawn | Marshall, Indiana |
| Babcock - Lake George 345 kV | J1742 | Solar | 294.1 MW | withdrawn | Porter, Indiana |
| Other_ | J3564 | Wind | 275.0 MW | operational | Newton, Indiana |
| Sheffield - Burnham 345 (Tie line between CE and NIPS, NIPS owns 1.87 miles) | J3008 | Battery | 270.0 MW | withdrawn | Cook, Illinois |
| Lake George - Schahfer GEN STA 345 kV Line Tap | J1412 | Solar | 250.0 MW | withdrawn | Porter County, Indiana |
| Schahfer - Green Acres 345kV Line | J1447 | Solar | 250.0 MW | withdrawn | Porter County, Indiana |
| E. Winamac - Monticello 138 kV line | J2798 | Solar | 250.0 MW | withdrawn | White, Indiana |
| EAST WINAMAC-MONTICELLO 138kV | J2723 | Wind | 249.0 MW | withdrawn | Vermillion, Indiana |
| Reynolds--Burr Oak 345kV line | J2849 | Solar | 245.0 MW | operational | Pulaski, Indiana |
| Reynolds - Burr Oak 345kV Line | J1067 | Solar | 240.0 MW | operational | Jasper County,Pulaski County, Indiana |
| Other_ | J3846 | Wind | 220.0 MW | withdrawn | Newton, Indiana |
| Reynolds 345kV Substation | J837 | Wind | 200.1 MW | operational | White County, Indiana |
| Reynolds 345kV Substation | J838 | Wind | 200.1 MW | operational | White County, Indiana |
| LEESBURG | J3357 | Battery | 200.0 MW | operational | Kosciusko, Indiana |
| Reynolds 345KV | J1627 | Wind | 200.0 MW | withdrawn | White, Indiana |
| GOODLAND - MORRISON DITCH 138.0kV | J2226 | Solar | 200.0 MW | withdrawn | Newton, Indiana |
| SCHAHFER GEN STA - BURR OAK 345.0kV | J1684 | Solar | 200.0 MW | operational | Starke, Indiana |
| Goodland to Reynolds 138KV | J1628 | Wind | 200.0 MW | withdrawn | White, Indiana |
| Reynolds 345kV Substation | J968 | Wind | 200.0 MW | operational | Jasper County,White County, Indiana |
| Rollin Schahfer - Lake George 345kV Line | J1332 | Solar | 200.0 MW | withdrawn | Jasper County, Indiana |
| HIPLE | J2213 | Battery | 200.0 MW | operational | Marshall, Indiana |
| Reynolds 345KV | J1772 | Solar | 200.0 MW | operational | White, Indiana |
| Rollin Schahfer (17SCHAHFER 255110) 345 kV | J2959 | Solar | 200.0 MW | withdrawn | Starke, Indiana |
| Reynolds - Burr Oak 345 kV Line | J2663 | Battery | 200.0 MW | withdrawn | White, Indiana |
| Goodland Substation 138kV (Bus Name: 17Goodland) | J1662 | Solar | 200.0 MW | withdrawn | Newton, Indiana |
| Reynolds 345kV Substation | J913 | Solar | 200.0 MW | operational | White County, Indiana |
| Reynold 345kV substation | J740 | Wind | 200.0 MW | withdrawn | Jasper County,Pulaski County, Indiana |
| HIPLE | J3291 | Battery | 200.0 MW | operational | LaGrange, Indiana |
| REYNOLDS | J3691 | Battery | 200.0 MW | operational | White, Indiana |
| Reynolds 345kV Substation | J1069 | Wind | 200.0 MW | operational | Jasper County,Pulaski County, Indiana |
| Reynolds - Burr 345kV | J1726 | Solar | 200.0 MW | withdrawn | Pulaski, Indiana |
| Morrison Ditch 345 kV substation (LRTP projects 15 & 16) - BUS #255210 | J3503 | Solar | 200.0 MW | withdrawn | Newton, Indiana |
| Schahfer - Burr Oak 345kV Line | J1335 | Solar | 199.5 MW | operational | Jasper County,Starke County, Indiana |
| Schahfer - Burr Oak 345kV Line | J1333 | Solar | 199.5 MW | operational | Jasper County,Starke County, Indiana |
| Schahfer - Burr Oak 345kV Line | J1340 | Solar | 199.5 MW | operational | Jasper County,Starke County, Indiana |
| Schahfer - Burr Oak 345kV Line | J1334 | Solar | 199.5 MW | operational | Jasper County,Starke County, Indiana |
| Schahfer - Burr Oak 345kV Line | J1336 | Solar | 199.5 MW | operational | Jasper County,Starke County, Indiana |
| Schahfer - Burr Oak 345kV Line | J1339 | Solar | 199.5 MW | operational | Jasper County,Starke County, Indiana |
| EAST WINAMAC - MONTICELLO 138.0kV | J3257 | Solar | 190.0 MW | withdrawn | Pulaski, Indiana |
| REYNOLDS - BURR OAK 345.0kV | J2353 | Solar | 190.0 MW | withdrawn | White, Indiana |
| Reynolds--Burr Oak 345kV Line | J2847 | Solar | 180.0 MW | operational | Starke, Indiana |
| Leesburg 345 kV | J2512 | Solar | 173.0 MW | withdrawn | Kosciusko, Indiana |
| Stillwell 138kV Subtation | J1355 | Battery | 160.0 MW | operational | LaPorte County, Indiana |
| Schahfer 345 kV Sub | J2144 | Gas | 155.2 MW | withdrawn | Jasper, Indiana |
| Monticello - Springboro 138 kV Line Tap | J1482 | Solar | 150.0 MW | operational | White County, Indiana |
| MISO Queue Project J4266 — Generation in an unlisted county, the U.S. | J4266 | — | 150.0 MW | operational | — |
| Burr Oak 138kV | J1802 | Solar | 150.0 MW | withdrawn | Marshall, Indiana |
| LNG - STILLWELL 138kV line | J1724 | Solar | 150.0 MW | operational | LaPorte, Indiana |
| Leesburg 138kV Substation | J1112 | Solar | 150.0 MW | withdrawn | Kosciusko County, Indiana |
| BABCOCK-STILLWELL 345 kV | J3225 | Solar | 150.0 MW | withdrawn | LaPorte, Indiana |
| MORRISON DITCH | S1163 | Battery | 150.0 MW | operational | Newton, Indiana |
| Green Acres138kV Subtation | J1353 | Battery | 150.0 MW | withdrawn | Lake County, Indiana |
| MISO Queue Project J4490 — Generation in an unlisted county, the U.S. | J4490 | — | 150.0 MW | operational | — |
| MORRISON DITCH | J1646 | Solar | 150.0 MW | operational | Newton, Indiana |
| MISO Queue Project J4398 — Generation in an unlisted county, the U.S. | J4398 | — | 150.0 MW | operational | — |
| GOODLAND - MORRISON DITCH 138.0kV | J3673 | Solar | 150.0 MW | withdrawn | Newton, Indiana |
| MISO Queue Project J4393 — Generation in an unlisted county, the U.S. | J4393 | — | 150.0 MW | operational | — |
| BABCOCK - STILLWELL 345.0kV | J3679 | Solar | 149.0 MW | operational | LaPorte, Indiana |
| Burr Oak 138kV | J2418 | Battery | 140.0 MW | withdrawn | Marshall, Indiana |
| REYNOLDS - BURR OAK 345.0kV | J2657 | Battery | 138.0 MW | withdrawn | White, Indiana |
| BURR OAK - PLYMOUTH 138.0kV | J3226 | Solar | 130.0 MW | withdrawn | Marshall, Indiana |
| Luchtman - Michigan City138kV Line | J1358 | Battery | 125.0 MW | operational | LaPorte County, Indiana |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-11-20 | MISO Queue Project S1195 — Generation in an unlisted county, the U.S. | new_project | — | operational |
| 2026-11-08 | MISO Queue Project J4490 — Generation in an unlisted county, the U.S. | new_project | — | operational |
| 2026-11-05 | South Valparaiso 138 kV Substation | withdrawn_date | — | 2026-10-20 |
| 2026-11-05 | South Valparaiso 138 kV Substation | status | operational | withdrawn |
| 2026-11-05 | Reynolds - Burr Oak 345 kV Line | withdrawn_date | — | 2026-10-20 |
| 2026-11-05 | Reynolds - Burr Oak 345 kV Line | status | operational | withdrawn |
| 2026-11-05 | REYNOLDS - BURR OAK 345.0kV | withdrawn_date | — | 2026-10-20 |
| 2026-11-05 | REYNOLDS - BURR OAK 345.0kV | status | operational | withdrawn |
| 2026-11-05 | REYNOLDS | withdrawn_date | — | 2026-10-20 |
| 2026-11-05 | REYNOLDS | status | operational | withdrawn |
| 2026-11-05 | J3578 | withdrawn_date | — | 2026-10-20 |
| 2026-11-05 | J3578 | status | operational | withdrawn |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26
Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Track queue activity connecting through NORTHERN INDIANA PUBLIC SERVICE COMPANY.