Edgewood BESS 1 (27INR0317)

Edgewood BESS 1 is a 102.1 MW other interconnection project in Van Zandt, Texas with a current status of operational. It is proposed to connect at Tap Edgewood 138kV bus(3181) to CANTNSW_8 (3174).

102.1 MWCapacity
OperationalStatus
Van ZandtMarket
OtherTechnology

Project facts

Canonical nameEdgewood BESS 1
Queue ID27INR0317
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketVan Zandt
TechnologyOther
Capacity102.1 MW
StateTexas
CountyVan Zandt
Point of interconnectionTap Edgewood 138kV bus(3181) to CANTNSW_8 (3174)
Requested (queue) date2024-11-21
Proposed in-service date
Operational date2028-03-01
Withdrawn date
DeveloperTempus Power management LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.