Everetts 34.5kV (AA1-067)

Everetts 34.5kV is a 15.0 MW solar interconnection project in Martin, North Carolina with a current status of operational.

15.0 MWCapacity
OperationalStatus
Market
SolarTechnology

Project facts

Canonical nameEveretts 34.5kV
Queue IDAA1-067
Statusoperational
Source statusIn Service
Market
TechnologySolar
Capacity15.0 MW
StateNorth Carolina
CountyMartin
Point of interconnection
Requested (queue) date2014-09-30
Proposed in-service date
Operational date2016-12-31
Withdrawn date
Developer
Utility / transmission ownerDominion

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata