North Carolina Interconnection Projects
interXdata tracks 1,989 interconnection projects in North Carolina representing 135,651 MW of requested capacity. The dominant technology by capacity is Gas. The most active counties are Wayne, Robeson, Duplin.
1,989Total projects
243Active
1,291Operational
448Withdrawn
135,651 MWRequested capacity
24,546 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 265 | 62,973 MW |
| Solar | 1,269 | 41,491 MW |
| Other | 288 | 20,120 MW |
| Battery | 140 | 8,010 MW |
| Wind | 19 | 2,957 MW |
| Diesel | 4 | 52 MW |
| Solar+Battery | 2 | 40 MW |
| Hydro | 2 | 8 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Wayne | 80 | 4,704 MW |
| Robeson | 73 | 2,101 MW |
| Duplin | 65 | 1,542 MW |
| Hertford | 54 | 1,465 MW |
| Richmond | 54 | 4,736 MW |
| Halifax | 49 | 1,700 MW |
| Bladen | 49 | 1,676 MW |
| Nash | 43 | 1,148 MW |
| Cleveland | 43 | 4,388 MW |
| Cumberland | 43 | 3,819 MW |
| Johnston | 40 | 1,009 MW |
| Wake | 39 | 6,792 MW |
| Bertie | 39 | 2,164 MW |
| Gaston | 38 | 1,822 MW |
| Edgecombe | 36 | 2,310 MW |
| Scotland | 36 | 1,559 MW |
| Rowan | 35 | 8,591 MW |
| Rockingham | 34 | 3,217 MW |
| Montgomery | 34 | 804 MW |
| Craven | 33 | 457 MW |
| Person | 32 | 15,917 MW |
| Anson | 31 | 3,419 MW |
| Buncombe | 31 | 2,552 MW |
| Lincoln | 30 | 3,773 MW |
| Columbus | 29 | 1,277 MW |
| Pitt | 28 | 556 MW |
| Lenoir | 28 | 721 MW |
| Martin | 27 | 478 MW |
| Davidson | 26 | 5,129 MW |
| Washington | 26 | 2,344 MW |
| Catawba | 26 | 3,592 MW |
| Randolph | 25 | 203 MW |
| Jones | 24 | 1,262 MW |
| Wilson | 24 | 1,394 MW |
| Currituck | 24 | 1,721 MW |
| Onslow | 23 | 1,571 MW |
| Moore | 22 | 216 MW |
| Guilford | 21 | 286 MW |
| Sampson | 20 | 388 MW |
| Northampton | 20 | 479 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Masked | 977726 | Gas | 1,620.0 MW | withdrawn | Rowan, North Carolina |
| Masked | 073054 | Gas | 1,503.0 MW | withdrawn | Davidson, North Carolina |
| Duke Energy Progress, LLC | 958347 | Gas | 1,455.0 MW | active | Person, North Carolina |
| Duke Energy Carolinas, LLC | CC100059 | Gas | 1,442.9 MW | active | Davie, North Carolina |
| Duke Energy Carolinas, LLC | 977731 | Gas | 1,394.9 MW | active | Davie, North Carolina |
| Duke Energy Carolinas | 034816 | Gas | 1,350.0 MW | withdrawn | Davidson, North Carolina |
| Duke Energy Progress, LLC | 113970 | Gas | 1,350.0 MW | withdrawn | Person, North Carolina |
| Duke Energy Progress, LLC | 033170 | Gas | 1,350.0 MW | withdrawn | Person, North Carolina |
| Duke Energy Progress, LLC | 072278 | Gas | 1,350.0 MW | withdrawn | Person, North Carolina |
| Duke Energy Progress, LLC | 043498 | Gas | 1,350.0 MW | withdrawn | Person, North Carolina |
| Duke Energy Progress, LLC | 030612 | Gas | 1,350.0 MW | withdrawn | Wake, North Carolina |
| Duke Energy Progress, LLC | 043510 | Gas | 1,350.0 MW | withdrawn | Person, North Carolina |
| Duke Energy Progress, LLC | 043466 | Gas | 1,350.0 MW | withdrawn | Person, North Carolina |
| Duke Energy Progress, LLC | 043484 | Gas | 1,350.0 MW | withdrawn | Person, North Carolina |
| Belews Creek | 8042_1 | Gas | 1,245.6 MW | operational | Stokes, North Carolina |
| Belews Creek | 8042_2 | Gas | 1,245.6 MW | operational | Stokes, North Carolina |
| Duke Energy Carolinas LLC | 017301 | Gas | 1,235.0 MW | withdrawn | Rowan, North Carolina |
| Duke Energy Carolinas LLC - Mill Creek CC | 017306 | Gas | 1,235.0 MW | withdrawn | Davidson, North Carolina |
| Duke Energy Progress, LLC | 017238 | Gas | 1,235.0 MW | withdrawn | Wake, North Carolina |
| Duke Energy Progress, LLC | 024735 | Gas | 1,235.0 MW | withdrawn | Cumberland, North Carolina |
| Duke Energy Progress, LLC | 024745 | Gas | 1,235.0 MW | withdrawn | Cumberland, North Carolina |
| McGuire | 6038_1 | Other | 1,220.3 MW | operational | Mecklenburg, North Carolina |
| McGuire | 6038_2 | Other | 1,220.3 MW | operational | Mecklenburg, North Carolina |
| Mackeys 230 kV | AF1-236 | Solar | 1,210.0 MW | withdrawn | Tyrell, North Carolina |
| Duke Energy Progress, LLC | 041400 | Other | 1,125.0 MW | withdrawn | Wake, North Carolina |
| Brunswick Nuclear | 6014_2 | Other | 1,001.6 MW | operational | Brunswick, North Carolina |
| Brunswick Nuclear | 6014_1 | Other | 1,001.6 MW | operational | Brunswick, North Carolina |
| Masked | 977454 | Gas | 990.0 MW | active | Anson, North Carolina |
| Harris (NC) | 6015_1 | Other | 950.9 MW | operational | Wake, North Carolina |
| Duke Energy Carolinas LLC | 956754 | Gas | 940.0 MW | withdrawn | Stokes, North Carolina |
Top developers in North Carolina
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Duke Energy Florida, LLC | 167 | 44,027 MW |
| RWE Solar Development, LLC | 6 | 600 MW |
| Otter Creek Wind Farm, LLC d/b/a Aurora Solar LLC | 2 | 200 MW |
| Merry Hill PV I, LLC | 2 | 110 MW |
| ACE Development Company, LLC | 2 | 225 MW |
| Voyager BESS, LLC | 1 | 185 MW |
| Parnell Solar, LLC | 1 | 20 MW |
| Creswell HWY 64 Solar, LLC | 1 | 150 MW |
| Oak Valley Solar LLC | 1 | 23 MW |
| NC1 Ahoskie Central, LLC | 1 | 20 MW |
| Pitt Solar, LLC | 1 | 70 MW |
| Murphy Solar and Central Air | 1 | 126 MW |
| Park Solar, LLC | 1 | 20 MW |
| Warsaw 2 Surplus | 1 | 11 MW |
| Bridge Solar, LLC | 1 | 75 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-08-24 | Duke Energy Progress, LLC | poi_name | JACKSONVILLE - WOMMACK 115KV | Jacksonville - Wommack 115kV |
| 2026-08-24 | Duke Energy Progress, LLC | capacity_mw | 0.0 | 30 |
| 2026-08-24 | Masked | poi_name | JACKSONVILLE - WOMMACK 115KV | Jacksonville - Wommack 115kV |
| 2026-08-24 | Duke Energy Progress, LLC | poi_name | Jacksonville - New Bern 230 Kv | Jacksonville - New Bern 230 kV |
| 2026-08-24 | Duke Energy Progress, LLC | poi_name | Jacksonville - New Bern 230 Kv | Jacksonville - New Bern 230 kV |
| 2026-08-24 | Masked | developer | Friesian Holdings LLC | Masked |
| 2026-08-24 | Masked | developer | Tangent Energy Solutions, INC. | Masked |
| 2026-08-24 | Masked | new_project | — | active |
| 2026-08-24 | Masked | developer | NTE Carolinas, LLC | Masked |
| 2026-08-24 | Masked | developer | Monroe Solar Farm | Masked |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: duke-dec-oasis; duke-dep-oasis; U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.