Fergus Falls MRES/WMMPA (J3778)

Fergus Falls MRES/WMMPA is a 100.0 MW battery interconnection project in Otter Tail, Minnesota with a current status of withdrawn. It is proposed to connect at Fergus Falls MRES/WMMPA.

100.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology

Project facts

Canonical nameFergus Falls MRES/WMMPA
Queue IDJ3778
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyBattery
Capacity100.0 MW
StateMinnesota
CountyOtter Tail
Point of interconnectionFergus Falls MRES/WMMPA
Requested (queue) date2024-04-15
Proposed in-service date2028-08-15
Operational date2028-08-15
Withdrawn date2025-09-30
Developer—
Utility / transmission ownerMISSOURI RIVER ENERGY SERVICES - TRANSMISSION

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-24phaseStudy Not StartedPhase 2low
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.