Ford-Cedarville 138 kV (AE2-318)

Ford-Cedarville 138 kV is a 100.0 MW solar interconnection project in Clermont, Ohio with a current status of suspended.

100.0 MWCapacity
SuspendedStatus
Market
SolarTechnology

Project facts

Canonical nameFord-Cedarville 138 kV
Queue IDAE2-318
Statussuspended
Source statusSuspended
Market
TechnologySolar
Capacity100.0 MW
StateOhio
CountyClermont
Point of interconnection
Requested (queue) date2019-03-31
Proposed in-service date2025-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerDEOK

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectsuspendedhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.