Clermont County, Ohio — Interconnection Projects
The interXdata warehouse tracks 26 interconnection projects in Clermont, Ohio, representing 2,178 MW of requested capacity.
26Total projects
0Active
9Operational
15Withdrawn
2,178 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 12 | 1,294 MW |
| Battery | 8 | 382 MW |
| Coal | 2 | 382 MW |
| Other | 4 | 120 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Zimmer 345 kV | AJ1-008 | Solar | 800.0 MW | withdrawn | Clermont, Ohio |
| MISO Queue Project G989 — Coal in Clermont, Ohio | G989 | Coal | 330.0 MW | operational | Clermont, Ohio |
| Cedarville 138 kV | AI1-167 | Battery | 250.0 MW | withdrawn | Clermont, Ohio |
| Ford-Cedarville 138 kV | AE2-318 | Solar | 100.0 MW | suspended | Clermont, Ohio |
| Ford-Cedarville 138 kV | AG2-118 | Solar | 84.0 MW | withdrawn | Clermont, Ohio |
| Nestlewood Solar | 65215_NSTLW | Solar | 80.0 MW | operational | Clermont, Ohio |
| S. Bethel-Brown 69kV | AC2-088 | Solar | 70.0 MW | operational | Clermont, Ohio |
| Cedarville-Ford 138 kV | AF1-315 | Solar | 60.0 MW | withdrawn | Clermont, Ohio |
| Cedarville-Ford 138 kV | AF1-045 | Battery | 52.2 MW | suspended | Clermont, Ohio |
| Cedarville-Ford 138 kV | AE2-329 | Battery | 52.2 MW | withdrawn | Clermont, Ohio |
| MISO Queue Project G990 — Coal in Clermont, Ohio | G990 | Coal | 52.0 MW | operational | Clermont, Ohio |
| W.H. Zimmer Station | Y3-073 | Other | 50.0 MW | withdrawn | Clermont, Ohio |
| W.H. Zimmer 345kV | AB2-156 | Other | 50.0 MW | withdrawn | Clermont, Ohio |
| Burns 69 kV | AH1-614 | Solar | 40.0 MW | withdrawn | Clermont, Ohio |
| W.H. Zimmer Station 345kV | AC1-182 | Other | 20.0 MW | withdrawn | Clermont, Ohio |
| Eastwood 34.5kV | AC2-086 | Solar | 20.0 MW | withdrawn | Clermont, Ohio |
| Eastwood 34kV | AC2-085 | Solar | 20.0 MW | withdrawn | Clermont, Ohio |
| Beckjord 138kV | AB2-178 | Battery | 19.8 MW | withdrawn | Clermont, Ohio |
| Eastwood 138kV | AC2-095 | Solar | 10.0 MW | withdrawn | Clermont, Ohio |
| South Bethel-Brown 69 kV | AD1-136 | Solar | 10.0 MW | operational | Clermont, Ohio |
| Beckjord 2 MW-2 | Y3-100 | Battery | 2.0 MW | withdrawn | Clermont, Ohio |
| Walter C Beckjord | 2830_BECK2 | Battery | 2.0 MW | operational | Clermont, Ohio |
| Beckjord 2 MW-1 | Y3-099 | Battery | 2.0 MW | operational | Clermont, Ohio |
| Walter C Beckjord | 2830_BECK1 | Battery | 2.0 MW | operational | Clermont, Ohio |
| Ford - Ceddarville 138 kV | AI2-348 | Solar | 0.0 MW | withdrawn | Clermont, Ohio |
| Pierce-Beckjord 138kV | Y3-064 | Other | — | operational | Clermont, Ohio |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.