French Goldston Solar (20INR0044)

French Goldston Solar is a 144.0 MW solar interconnection project in Young, Texas with a current status of withdrawn. It is proposed to connect at tap 345kV 1430 Graham - 1445 Burwick Switch.

144.0 MWCapacity
WithdrawnStatus
ERCOTMarket
SolarTechnology

Project facts

Canonical nameFrench Goldston Solar
Queue ID20INR0044
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologySolar
Capacity144.0 MW
StateTexas
CountyYoung
Point of interconnectiontap 345kV 1430 Graham - 1445 Burwick Switch
Requested (queue) date2018-01-02
Proposed in-service date2023-12-15
Operational date
Withdrawn date2021-09-01
DeveloperBelltown Power
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.