Friend 115kV (GEN-2014-039)

Friend 115kV is a 73.4 MW wind interconnection project in Saline, Nebraska with a current status of withdrawn. It is proposed to connect at Friend 115kV.

73.4 MWCapacity
WithdrawnStatus
NEMarket
WindTechnology

Project facts

Canonical nameFriend 115kV
Queue IDGEN-2014-039
Statuswithdrawn
Source statusWITHDRAWN
MarketNE
TechnologyWind
Capacity73.4 MW
StateNebraska
CountySaline
Point of interconnectionFriend 115kV
Requested (queue) date2014-09-29
Proposed in-service date2021-07-01
Operational date
Withdrawn date2022-01-09
Developer
Utility / transmission ownerNPPD

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.