Garner-Lancaster 115 kV (AG1-135 - moved to TC1)

Garner-Lancaster 115 kV is a 60.0 MW solar interconnection project in Richmond, Virginia with a current status of operational.

60.0 MWCapacity
OperationalStatus
—Market
SolarTechnology

Project facts

Canonical nameGarner-Lancaster 115 kV
Queue IDAG1-135 - moved to TC1
Statusoperational
Source statusPartially in Service - Under Construction
Market—
TechnologySolar
Capacity60.0 MW
StateVirginia
CountyRichmond
Point of interconnection—
Requested (queue) date2020-09-03
Proposed in-service date—
Operational date2031-03-01
Withdrawn date—
Developer—
Utility / transmission ownerDominion

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—operationalhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata