Georgia Power IC-215 (IC-215)
Georgia Power IC-215 is a 1,200.0 MW gas interconnection project in Early County, Georgia with a current status of withdrawn. It is proposed to connect at Farley - Raccoon Creek 500 kV line.
1,200.0 MWCapacity
WithdrawnStatus
GAMarket
GasTechnology
Project facts
| Canonical name | Georgia Power IC-215 |
|---|---|
| Queue ID | IC-215 |
| Status | withdrawn |
| Source status | — |
| Market | GA |
| Technology | Gas |
| Capacity | 1,200.0 MW |
| State | Georgia |
| County | Early County |
| Point of interconnection | Farley - Raccoon Creek 500 kV line |
| Requested (queue) date | 2005-03-10 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | 2012-04-22 |
| Developer | — |
| Utility / transmission owner | Georgia Power |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata