Early County County, Georgia — Interconnection Projects

The interXdata warehouse tracks 15 interconnection projects in Early County, Georgia, representing 5,581 MW of requested capacity.

15Total projects
2Active
6Operational
7Withdrawn
5,581 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Gas64,550 MW
Solar8531 MW
Battery1500 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Georgia Power IC-215IC-215Gas1,200.0 MWwithdrawnEarly County, Georgia
Georgia Power IC-216IC-216Gas1,200.0 MWwithdrawnEarly County, Georgia
Georgia Power IC-222IC-222Gas700.0 MWwithdrawnEarly County, Georgia
Georgia Power IC-217IC-217Gas700.0 MWwithdrawnEarly County, Georgia
Georgia Power IC-121IC-121Gas550.0 MWwithdrawnEarly County, Georgia
Georgia Power 26-IC-145926-IC-1459Battery500.0 MWactiveEarly County, Georgia
Georgia Power IC-223IC-223Gas200.0 MWwithdrawnEarly County, Georgia
Early SolarIC-562Solar125.0 MWoperationalEarly County, Georgia
Georgia Power IC-324IC-324Solar80.0 MWwithdrawnEarly County, Georgia
Five Bridges SolarIC-883Solar80.0 MWoperationalEarly County, Georgia
Georgia Power IC-1001IC-1001Solar80.0 MWactiveEarly County, Georgia
Hightower SolarIC-981Solar80.0 MWoperationalEarly County, Georgia
Early SolarIC-578Solar46.0 MWoperationalEarly County, Georgia
Rising Paladin Solar FarmIC-266Solar20.0 MWoperationalEarly County, Georgia
Rising Paladin Solar FarmIC-270Solar20.0 MWoperationalEarly County, Georgia

Top developers

Developer attribution is not yet resolved for this set.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get an alert when a new project is proposed in Early County County.

Start tracking with interXdata