Glass Mountain BB Solar 2 is a 302.7 MW solar interconnection project in Pecos, Texas with a current status of active. It is proposed to connect at Tap 345kV 6040 Solstice to 38441 Bottlebrush.

302.7 MWCapacity
ActiveStatus
PecosMarket
SolarTechnology

Project facts

Canonical nameGlass Mountain BB Solar 2
Queue ID29INR0348
Statusactive
Source statusSS Started, FIS Started, No IA
MarketPecos
TechnologySolar
Capacity302.7 MW
StateTexas
CountyPecos
Point of interconnectionTap 345kV 6040 Solstice to 38441 Bottlebrush
Requested (queue) date2026-06-11
Proposed in-service date2029-03-01
Operational date
Withdrawn date
DeveloperGlass Mountain Solar, LLC
Utility / transmission ownerERCOT

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.