Glass Mountain Solar, LLC — Interconnection Portfolio
Glass Mountain Solar, LLC is associated with 8 tracked interconnection projects representing 2,419 MW of requested capacity.
Entity resolution: this developer rolls up 5 source organization name(s) that were auto-matched into a single canonical cluster. Attribution is inferred from source records and may include related special-purpose entities.
8Projects
0Active
8Operational
0Withdrawn
2,419 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 8 | 2,419 MW |
Geographic footprint
| State | Projects |
|---|---|
| Texas | 8 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Glass Mountain BB Solar 2 | 29INR0348 | Solar | 302.7 MW | operational | Pecos, Texas |
| Glass Mountain BB Solar 1 | 29INR0347 | Solar | 302.7 MW | operational | Pecos, Texas |
| Glass Mountain BB Solar 4 | 29INR0358 | Solar | 302.6 MW | operational | Pecos, Texas |
| Glass Mountain BB Solar 5 | 29INR0349 | Solar | 302.6 MW | operational | Pecos, Texas |
| Glass Mountain BB Solar 3 | 29INR0357 | Solar | 302.6 MW | operational | Pecos, Texas |
| Pecos Flats Solar | 29INR0181 | Solar | 302.4 MW | operational | Pecos, Texas |
| Pecos Flats Solar III | 29INR0183 | Solar | 301.5 MW | operational | Pecos, Texas |
| Pecos Flats Solar II | 29INR0182 | Solar | 301.5 MW | operational | Pecos, Texas |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-09-30 | Glass Mountain BB Solar 4 | phase | SS Started, FIS Started, No IA | SS Completed, FIS Started, No IA |
| 2026-09-30 | Glass Mountain BB Solar 4 | operational_date | — | 2029-10-01 |
| 2026-09-30 | Glass Mountain BB Solar 4 | proposed_online_date | 2029-10-01 | — |
| 2026-09-30 | Glass Mountain BB Solar 4 | status | active | operational |
| 2026-09-30 | Glass Mountain BB Solar 3 | phase | SS Started, FIS Started, No IA | SS Completed, FIS Started, No IA |
| 2026-09-30 | Glass Mountain BB Solar 3 | operational_date | — | 2029-10-01 |
| 2026-09-30 | Glass Mountain BB Solar 3 | proposed_online_date | 2029-10-01 | — |
| 2026-09-30 | Glass Mountain BB Solar 3 | status | active | operational |
| 2026-09-30 | Glass Mountain BB Solar 5 | phase | SS Started, FIS Started, No IA | SS Completed, FIS Started, No IA |
| 2026-09-30 | Glass Mountain BB Solar 5 | operational_date | — | 2029-10-01 |
| 2026-09-30 | Glass Mountain BB Solar 5 | proposed_online_date | 2029-10-01 | — |
| 2026-09-30 | Glass Mountain BB Solar 5 | status | active | operational |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-10-12
Page data generated2026-10-12
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.