Grand Prairie-Grand Island (Holt County NE) 345kV (GEN-2015-023)

Grand Prairie-Grand Island (Holt County NE) 345kV is a 300.7 MW wind interconnection project in Antelope & Wheeler County, Nebraska with a current status of operational. It is proposed to connect at Grand Prairie-Grand Island (Holt County NE) 345kV.

300.7 MWCapacity
OperationalStatus
NEMarket
WindTechnology

Project facts

Canonical nameGrand Prairie-Grand Island (Holt County NE) 345kV
Queue IDGEN-2015-023
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketNE
TechnologyWind
Capacity300.7 MW
StateNebraska
CountyAntelope & Wheeler County
Point of interconnectionGrand Prairie-Grand Island (Holt County NE) 345kV
Requested (queue) date2015-03-31
Proposed in-service date
Operational date2019-12-31
Withdrawn date
Developer
Utility / transmission ownerNPPD

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.