GRE-BENTON 7 115kV (S1088)

GRE-BENTON 7 115kV is a 100.0 MW battery interconnection project in Benton, Minnesota with a current status of operational. It is proposed to connect at GRE-BENTON 7 115kV.

100.0 MWCapacity
OperationalStatus
Market
BatteryTechnology

Project facts

Canonical nameGRE-BENTON 7 115kV
Queue IDS1088
Statusoperational
Source statusActive
Market
TechnologyBattery
Capacity100.0 MW
StateMinnesota
CountyBenton
Point of interconnectionGRE-BENTON 7 115kV
Requested (queue) date2025-03-17
Proposed in-service date2027-06-30
Operational date2027-06-30
Withdrawn date
Developer
Utility / transmission ownerGREAT RIVER ENERGY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.