Griffin Trail Wind (20INR0052)

Griffin Trail Wind is a 225.6 MW wind interconnection project in Knox, Texas with a current status of operational. It is proposed to connect at 60506 AVOGADRO 345 kV.

225.6 MWCapacity
OperationalStatus
ERCOTMarket
WindTechnology

Project facts

Canonical nameGriffin Trail Wind
Queue ID20INR0052
Statusoperational
Source statusoperational
MarketERCOT
TechnologyWind
Capacity225.6 MW
StateTexas
CountyKnox
Point of interconnection60506 AVOGADRO 345 kV
Requested (queue) date2018-03-04
Proposed in-service date2021-10-31
Operational date2021-10-28
Withdrawn date
DeveloperInnergex
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.