Hackberry Draw Solar (30INR0146)
Hackberry Draw Solar is a 653.0 MW solar interconnection project in Jones, Texas with a current status of active. It is proposed to connect at Tap 345 kV (68000) West Shackleford - (60515) Clear Crossing Ckt 2 .
653.0 MWCapacity
ActiveStatus
JonesMarket
SolarTechnology
Project facts
| Canonical name | Hackberry Draw Solar |
|---|---|
| Queue ID | 30INR0146 |
| Status | active |
| Source status | SS Started, FIS Started, No IA |
| Market | Jones |
| Technology | Solar |
| Capacity | 653.0 MW |
| State | Texas |
| County | Jones |
| Point of interconnection | Tap 345 kV (68000) West Shackleford - (60515) Clear Crossing Ckt 2 |
| Requested (queue) date | 2026-08-03 |
| Proposed in-service date | 2030-04-30 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Orsted Onshore Development North America, LLC |
| Utility / transmission owner | ERCOT |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-31 | new_project | — | active | high |
Explore related data
Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata