Halyard Wharton (16INR0044)

Halyard Wharton is a 484.0 MW gas interconnection project in Wharton, Texas with a current status of suspended. It is proposed to connect at tap 345kV 9073 Holman - 44200 Hillje.

484.0 MWCapacity
SuspendedStatus
ERCOTMarket
GasTechnology

Project facts

Canonical nameHalyard Wharton
Queue ID16INR0044
Statussuspended
Source statussuspended
MarketERCOT
TechnologyGas
Capacity484.0 MW
StateTexas
CountyWharton
Point of interconnectiontap 345kV 9073 Holman - 44200 Hillje
Requested (queue) date2014-03-16
Proposed in-service date2021-06-01
Operational date
Withdrawn date
DeveloperHalyard Energy
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata