Hanson Storage (24INR0057)

Hanson Storage is a 101.4 MW battery interconnection project in Coleman, Texas with a current status of withdrawn. It is proposed to connect at tap 345kV 1444 Brown - 11406 Central Bluff.

101.4 MWCapacity
WithdrawnStatus
ERCOTMarket
BatteryTechnology

Project facts

Canonical nameHanson Storage
Queue ID24INR0057
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologyBattery
Capacity101.4 MW
StateTexas
CountyColeman
Point of interconnectiontap 345kV 1444 Brown - 11406 Central Bluff
Requested (queue) date2021-06-20
Proposed in-service date2027-04-17
Operational date
Withdrawn date2025-01-22
DeveloperHanson Solar, LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.