Harrowgate 34 kV (AE2-212)
Harrowgate 34 kV is a 20.0 MW solar interconnection project in Chesterfield, Virginia with a current status of active.
20.0 MWCapacity
ActiveStatus
—Market
SolarTechnology
Project facts
| Canonical name | Harrowgate 34 kV |
|---|---|
| Queue ID | AE2-212 |
| Status | active |
| Source status | Engineering and Procurement |
| Market | — |
| Technology | Solar |
| Capacity | 20.0 MW |
| State | Virginia |
| County | Chesterfield |
| Point of interconnection | — |
| Requested (queue) date | 2019-03-20 |
| Proposed in-service date | 2027-06-30 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Dominion |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | active | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.