Hatfield 500kV (AC2-142)

Hatfield 500kV is a 129.7 MW gas interconnection project in Greene, Pennsylvania with a current status of operational.

129.7 MWCapacity
OperationalStatus
—Market
GasTechnology

Project facts

Canonical nameHatfield 500kV
Queue IDAC2-142
Statusoperational
Source statusIn Service
Market—
TechnologyGas
Capacity129.7 MW
StatePennsylvania
CountyGreene
Point of interconnection—
Requested (queue) date2017-03-28
Proposed in-service date—
Operational date2021-05-09
Withdrawn date—
Developer—
Utility / transmission ownerAPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—operationalhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.