Greene County, Pennsylvania — Interconnection Projects
The interXdata warehouse tracks 31 interconnection projects in Greene, Pennsylvania, representing 7,293 MW of requested capacity.
31Total projects
2Active
4Operational
25Withdrawn
7,293 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 10 | 3,674 MW |
| Other | 6 | 2,767 MW |
| Solar | 13 | 682 MW |
| Battery | 2 | 170 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Hatfield 500kV | AA1-070 | Other | 1,710.0 MW | withdrawn | Greene, Pennsylvania |
| Hatfield 500kV | AC2-025 | Gas | 1,140.0 MW | withdrawn | Greene, Pennsylvania |
| Hatfield 500kV | AC1-097 | Gas | 1,140.0 MW | withdrawn | Greene, Pennsylvania |
| Hill Top Energy Center, LLC | 62565_GEN1 | Gas | 664.7 MW | operational | Greene, Pennsylvania |
| Hatfield Ferry 500 kV | G51_W60 | Other | 525.0 MW | withdrawn | Greene, Pennsylvania |
| Hatfield 500 kV | L10 | Other | 520.0 MW | withdrawn | Greene, Pennsylvania |
| Hatfield 500kV | AA2-173 | Gas | 515.0 MW | operational | Greene, Pennsylvania |
| North Longview 500 kV | AI2-443 | Solar | 300.0 MW | withdrawn | Greene, Pennsylvania |
| Whiteley 138 kV | AH2-279 | Battery | 150.0 MW | withdrawn | Greene, Pennsylvania |
| Hatfield 500kV | AC2-142 | Gas | 129.7 MW | operational | Greene, Pennsylvania |
| Franklin 138 kV | AH1-367 | Solar | 74.0 MW | withdrawn | Greene, Pennsylvania |
| Franklin 138 kV II | AH1-367A - moved to TC2 | Solar | 72.0 MW | withdrawn | Greene, Pennsylvania |
| Iron Javelin Emerald | AH1-367A | Solar | 72.0 MW | withdrawn | Greene, Pennsylvania |
| North Longview 500 kV | AF1-297 | Solar | 52.8 MW | withdrawn | Greene, Pennsylvania |
| Emerald 25 kV | AH2-295 | Solar | 40.0 MW | withdrawn | Greene, Pennsylvania |
| Whitely 138 kV | AH1-366 | Solar | 30.0 MW | withdrawn | Greene, Pennsylvania |
| Whiteley 25kV | AB1-164 | Battery | 20.0 MW | withdrawn | Greene, Pennsylvania |
| Franklin-Emerald 25 kV | AD2-002 | Gas | 20.0 MW | withdrawn | Greene, Pennsylvania |
| Hatfield 500kV | AB1-112 | Gas | 20.0 MW | operational | Greene, Pennsylvania |
| Franklin 25kV | AB1-171 | Gas | 20.0 MW | withdrawn | Greene, Pennsylvania |
| Garards Fort 25kV | Y2-088 | Gas | 19.9 MW | withdrawn | Greene, Pennsylvania |
| Greensboro 25 kV | AH1-647 | Solar | 19.9 MW | withdrawn | Greene, Pennsylvania |
| Buckeye No. 3 - Cowell Junction 25kV | AH1-373 | Solar | 12.8 MW | withdrawn | Greene, Pennsylvania |
| Mather - Stoney Point Junction 25 kV | AH1-370 | Solar | 8.0 MW | withdrawn | Greene, Pennsylvania |
| Grays Landing L&D Hydroelectric Project | 62388_NA1 | Other | 6.0 MW | active | Greene, Pennsylvania |
| Grays Landing L&D Hydroelectric Project | 62388_NA2 | Other | 6.0 MW | active | Greene, Pennsylvania |
| Emerald 6 25kV | K17 | Gas | 5.0 MW | withdrawn | Greene, Pennsylvania |
| Whitely 138 kV | AI2-184 | Solar | 0.0 MW | withdrawn | Greene, Pennsylvania |
| Franklin 138 kV | AI2-185 | Solar | 0.0 MW | withdrawn | Greene, Pennsylvania |
| Franklin 138 kV | AI2-186 | Solar | 0.0 MW | withdrawn | Greene, Pennsylvania |
| Black Oak - Hatfield Wave Trap | O15 | Other | — | withdrawn | Greene, Pennsylvania |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Emerald Renewable LLC | 1 | 72 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Greene County.
Start tracking with interXdata