HE Lewis Creek 69 kV (J1699)

HE Lewis Creek 69 kV is a 43.0 MW solar interconnection project in Shelby, Indiana with a current status of withdrawn. It is proposed to connect at HE Lewis Creek 69 kV.

43.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameHE Lewis Creek 69 kV
Queue IDJ1699
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity43.0 MW
StateIndiana
CountyShelby
Point of interconnectionHE Lewis Creek 69 kV
Requested (queue) date2020-06-25
Proposed in-service date2024-10-01
Operational date2024-10-01
Withdrawn date2023-07-17
Developer
Utility / transmission ownerHoosier Energy

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata