Shelby County, Indiana — Interconnection Projects
The interXdata warehouse tracks 12 interconnection projects in Shelby, Indiana, representing 3,801 MW of requested capacity.
12Total projects
0Active
2Operational
10Withdrawn
3,801 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 3 | 2,070 MW |
| Solar | 5 | 731 MW |
| Battery | 3 | 650 MW |
| Other | 1 | 350 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| MISO Queue Project J259 — Gas in Shelby, Indiana | J259 | Gas | 1,065.0 MW | withdrawn | Shelby, Indiana |
| MISO Queue Project J250 — Gas in Shelby, Indiana | J250 | Gas | 999.0 MW | withdrawn | Shelby, Indiana |
| MISO Queue Project G088 — Other in Shelby, Indiana | G088 | Other | 350.0 MW | withdrawn | Shelby, Indiana |
| Gwynneville to Sunnyside 345kV | J1756 | Solar | 309.0 MW | withdrawn | Shelby, Indiana |
| Hanna-Tanners Creek 345 kV | AG1-297 - moved to TC1 | Battery | 300.0 MW | withdrawn | Shelby, Indiana |
| Blue River Storage | AG1-297 | Battery | 300.0 MW | withdrawn | Shelby, Indiana |
| Speedway Solar, LLC | 66264_SDS | Solar | 199.0 MW | operational | Shelby, Indiana |
| DEI's Columbus to Clark Twp. 230 kV (one of the two 230 kV circuits going from Columbus to Five Poin | J1829 | Solar | 180.0 MW | withdrawn | Shelby, Indiana |
| Gwynneville 345kV Substation | J1704 | Battery | 50.0 MW | withdrawn | Shelby, Indiana |
| HE Lewis Creek 69 kV | J1699 | Solar | 43.0 MW | withdrawn | Shelby, Indiana |
| POET Biorefining - Shelbyville | 63921_1 | Gas | 6.1 MW | operational | Shelby, Indiana |
| Hanna - Tanners Creek 345 kV | AH1-013 | Solar | 0.0 MW | withdrawn | Shelby, Indiana |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Hecate Energy | 1 | 300 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Shelby County.
Start tracking with interXdata